1. Building Licence
 Category I
 Building Licence Request Up To 

      150m2 - Residential Purpose
      750m2 - Non Residential Purpose

    Application Under Section 272, 273, 288 of CCMC Act 1981 should be submitted in Zonal office.

    Along with the following enclosures addressed to the Assistant Commissioner of Concerned Zone

1. Building Plans  - 4 Copies.
2. Document  - 1 Copy Xerox
3. Topo Sketch - 1 Copy
4. Layout Copy - 1 Copy Xerox
5. Ministry of Works, Housing and
National Building Organization
Schedule II
- 2 Copy enclosed in Application Form
6. Town Survey Sketch - 1 Copy (No need for approved layout)
7. EC - 13 Years

     30 Days from the date of submission of application orders will be sent to applicant for LICENCE PERIOD ONE YEAR. If Satisfies Rule
 Category II
 Building Licence Request Up To 

      200m2 - Residential Purpose
      100m2 - Non Residential Purpose

    Procedures as per Category I .

    Application should be addressed to the Assistant Commissioner Coimbatore Corporation.

 Category III
  Building Licence Request Up To 

      More Than 200m2 - Residential Purpose
      More Than 100m2 - Non Residential Purpose

    Application for Building Licence should be submitted along with the following enclosure:

1. From 49 addressed to Member Secretary Local Planning Authority Coimbatore. 
2. Building Plan - 5 Copies Ammonia Prints
3. Document  - 5 Copies Xerox
4. EC - 13 Years - 5 Copies Xerox
5. Town Survey Sketch With Extract - 5 Copies (No need for approved layout)
6. Topo Sketch - 5 Copies Ammonia Prints
7. Scheme Extract - 5 Copies Ammonia Prints

     Within 30 Days from the date of submission of application, Proposal will be forwarded to LPA. After receiving orders from LPA, the Corporation will sent appropriate orders to the applicant based on LPA's order within 30 days.

2. Layout Approval
 Category I
  Permission Request up to an extent of 5 acres of Layout.

    Application will be received in Zonal Office along with the following enclosures, addressed the Member Secretary LPA through Commissioner Coimbatore Corporation. 

1. Layout Plans - 5 Copies Ammonia Prints
2. Document  - 5 Copies Xerox
3. No Land Acquisition Certificate - From Revenue Department 5 Copies
4. Layout Copy - From Revenue Department 5 Copies
5. Schedule Extract - 5 Copies Ammonia Prints
6. Topo Sketch - 5 Copies Ammonia Prints
7. Town Survey Sketch With Extract - 5 Copies
8. EC - 13 Years - 5 Copies

    15 Days from the date of submission of application, the proposal will be forwarded to Local Planning Authority after collecting 25% of development charges. After receiving orders from LPA, orders will be sent to the applicant within 30 days.
 Category II

    For layout having more than 5 acres extent of layout applicant should submit application in Zonal office addressed to the Commissioner of Town and Country Planning chennai through Commissioner Coimbatore Municipal Corporation with the following enclosures.

1. Layout Plan - 7 Copies Ammonia Prints
2. Document - 7 Copies
3. No encroachment Certificate.  - 7 Copies
4. No Land Acquisition Certificate - 7 Copies
5. Scheme Plan Extract - 7 CopiesAmmonia Prints
6. Topo Sketch - 7 Copies Ammonia Prints
7. Town survey sketch with Extract - 7 Copies
8. EC - 13 Years - 7 Copies
9. Master Plan Extract - 7 Copies

     15 Days from the date of submission. Proposal will be forwarded to CTCP through Member Secretary LPA after collecting 25% Layout development charges. After receiving Orders from CTCP and LPA. Approval orders will be sent to applicant within 30 Days.

3 & 4. Site Approval / Subdivision, Reconstitution of site Approval
  Permission Request up to an extent of 5 acres of Layout.

    Applications regarding the Subdivision o site, Reconstitution of site should be submitted to the Zonal office addressed to the Member Secretary  Local Planning Authority through Commissioner Coimbatore Municipal Corporation along with the following enclosure. 

1. Detailed Plan - 5 Copies Ammonia Prints
2. Document - 5 Copies
3. Scheme Plan Extract - 5 Copies Ammonia Prints
4. Topo Sketch - 5 Copies Ammonia Prints
5. own Survey Sketch With Extract - 5 Copies
6. EC - 13 Years - 5 Copies

    30 Days from the date of submission, applicant proposal will be forwarded to Local Planning Authority, after receiving orders from Local Planning Authority, orders will be sent to the applicant within 30 days.

5. Renewal Of Building Licence
 Category I
 Renewal of Building Licence Request Up To 

      150m2 - Residential
        75m2 - Non Residential

    Request for renewal of Licence should be submitted in Zonal Office addressed to the Assistant Commissioner Coimbatore Municipal Corporation along with the following enclosures.

1. Original Licence Order Proceeding. (Xerox) 
2. Approved Plan Copy. (Xerox)

     Within 30 Days from the date of submission of application, Renewal of Licence issued, if work has not commenced as per approved plan for one year from the date of expiry of original Licence period.
    After expiry of renewal of Licence period applicant should submit fresh application for Licence.
 Category II
 Renewal of Building Licence Request 

      150m2 - 200m2  Residential
        75m2 - 100m2  Non Residential

    Permission request for renewal of Licence should submit application in Zonal Office should be addressed to the Assistant Commissioner Coimbatore Municipal Corporation along with the following enclosures.

    Procedures as per Category I .

 Category III
     Building area

      More Than 200m2 - Residential
      More Than 100m2 - Non Residential buildings

    Applications in Zonal Office addressed to the Commissioner Coimbatore Municipal Corporation along with the following enclosures will be received.

    Request for renewal of licence should be submitted to Zonal Office addressed to the Assistant Commissioner along with the following documents.

1. Original Licence order proceeding. (Xerox)
2. Approved Plan copy (Xerox)

     30 Days from the date of submission, Renewal of Licence will be issued.

    
After expiry of renewal of Licence period applicant can submit fresh application for second Licence for a period of one year.

    After expiry of 3 years planning permission period applicant should submit fresh application for planning permission addressed to the Member Secretary Local Planning Authority through Commissioner Coimbatore Municipal Corporation in Zonal Office.

6 & 7. Request For Survey and Survey Extract
    Applications in Zonal Office addressed to the Assistant Commissioner Coimbatore Municipal Corporation should be submitted with document Xerox copy.

    15 Days from the date of submission of application will sent to applicant.

8. Request For Attested Copies 
    Applications in Zonal Office attested to the Assistant Commissioner Coimbatore Municipal Corporation along with detailed plans in Ammonia prints with original Licence order proceeding Xerox copy.

    7 Days from the date of submission of application attested copies will be issued to the applicant.

9. Appeals to Director of town and country planning OR to the Government.
    Applications addressed to DTCP OR Government through Commissioner Coimbatore Municipal Corporation and Local Planning Authority will be received in Zonal Office. Within 30 days of receipt of such application, the application will be forwarded to DTCP through LPA.